Select multiple processes for a conformance check
You can select one or more reference processes to perform a conformance check.
Prerequisites
You use ARIS Process Mining Advanced or Enterprise.
You added at least one reference process to a data set.
The reference processes must be available for the conformance check.
The reference processes must have an activated activity mapping.
Open the data set that contains the reference processes.
Click Compliance in the data set panel. The Compliance section opens with the Conformance page.
Click Add. The dialog to select reference processes opens. The dialog only provides processes that are available for the conformance check and their mapping is set to Complete or Modified.
Select one or more reference processes and click Add. The selected reference processes are listed on the Conformance page.
The state of the added processes is Not active. This means that the processes will not yet be used for the conformance check.
Select one or more reference processes on the Conformance page.
Click Activate.
If required, click Recalculate. You must trigger a recalculation if you activate a reference process or change the settings of activated reference processes.
The order of the reference processes in the list determines the calculation priority. To move a reference process in the list, select a process and click Move up or Move down. You can also move a line in the list with the mouse pointer by dragging and dropping it.
For more details, see the Define filters for the reference processes chapter.
You selected reference processes for the conformance check. The processes are labeled with the Active state.
To deactivate processes for the performance check, select the processes and click Deactivate. If you select multiple reference processes with different states, only the Activate option is available.
You can display more process details. Select a reference process in the list and click the Details icon. A panel with detailed information about the selected process is displayed.