Move an analysis

You can move an analysis from a project to another project if the source and target project use the same data set. If the target project uses a data set that is different from the data set used in the source project, you may need to map the fields used in the source data set to the appropriate fields in the target data set.

Procedure. Procedure
  1. Open a project.

  2. Move the mouse pointer over an analysis in the Project panel.

  3. Click the ... More options icon.

  4. Click Move to. A corresponding dialog opens.

  5. Select the project to which you want to move the analysis.

  6. Click Move here.

  7. If the target data set contains different fields than the source data set, you must select the fields that can be used instead. A corresponding dialog to map the fields opens.

    1. To display all fields, click Select all fields. By default, only the different fields are selected.

    2. To map a field from the target data set, click Select missing field. A panel with the fields of the target data set opens.

    3. Select a field to map.

  8. Click Apply.

The selected analysis is moved to the selected project.